Road Repair Report 3/8/13


 
 
Road Repair Update
March 8, 2013
 
-------------------------------------------------------------------------------------------------------------------

PROJECT:
Sylvan Avenue and Litt Road Improvements
STATUS:
Work is in progress. Project completion is expected for August 2013.
IMPACT:
Traffic controls are in place with one lane of travel on Sylvan Avenue from Millbrook Avenue to Claus Road. Motorists are requested to travel slowly through the work zone and use alternate routes when possible.
Note: Litt Road north of Sylvan Avenue to Plainview Road will be closed beginning Monday, October 8th through April 2013.

-------------------------------------------------------------------------------------------------------------------

PROJECT:
Carpenter Road Bridge Seismic Retrofit
STATUS:
Work is in progress. Project completion is expected for June 2013.
IMPACT:
Traffic controls are in place with narrow lanes and delays anticipated in effect Monday, March 11th through Friday, March 15th, 2013. Motorists are requested to travel slowly through the work zone and use alternate routes when possible. Oversized and Wide Load Vehicles should use alternate routes.

-------------------------------------------------------------------------------------------------------------------

PROJECT:
Gas Main Replacement by PG&E
STATUS:
Work is scheduled to resume Monday, March 18th. 
IMPACT:
Claratina Avenue from McHenry Avenue to Coffee Road will be restricted to alternating, one-way traffic control with flaggers and shoulder work along Coffee Road from Claratina Avenue to Claribel Road. Work will be Monday through Saturday 7:00 a.m. to 5:00 p.m. Drivers should expect delays. Motorists are advised to proceed with caution and pay attention to signage. Drivers should use alternate routes when possible to avoid delays. Electronic message board signs are in place to alert drivers of the upcoming road work. For further information about this work contact PG&E directly at (559) 317-8857.

-------------------------------------------------------------------------------------------------------------------

PROJECT:
Gas Main Work by PG&E
STATUS:
Work is suspended. Work will resume after the winter suspension beginning late-March 2013.
IMPACT:
Bangs Avenue from Dale Road to Carver Road will be restricted to alternating, one-way traffic control with flaggers and shoulder work along Bangs Avenue from Carver Road to Dale Road. Work will be Monday through Saturday 7:00 a.m. to 5:00 p.m. Drivers should expect delays. Motorists are advised to proceed with caution and pay attention to signage. Electronic message board signs are in place to alert drivers of the upcoming road work. Drivers should use alternate routes when possible. For further information about this work contact PG&E directly at (559) 317-8857.

-------------------------------------------------------------------------------------------------------------------

PROJECT:
Crack Sealing on Rumble Road
STATUS:
Work is in progress. Project completion is expected to end March 28, 2013.
IMPACT:
Work will take place on Rumble Road between Sisk Road and McHenry Avenue. Traffic controls and flaggers will be in place. Delays are anticipated. Motorists are requested to travel slowly through the work zone and use alternate routes when possible.

-------------------------------------------------------------------------------------------------------------------

PROJECT:
Hilltop Area Strengthen and Replace Water System
STATUS:
Work is in progress. Project completion is expected for June 6, 2013.
IMPACT:
Work will be ongoing with traffic controls and restrictions on Paradise Road from Vernon Ave to Ohio Ave and on Carpenter Road from Robertson Road to Paradise Road. Traffic controls and flaggers will be in place. Other impacted roads include: Dunning Lane, Regal Road, Ridge Road, Hilltop Lane, and Robertson Road. Motorists are requested to travel slowly through the work zone and use alternate routes when possible.

-------------------------------------------------------------------------------------------------------------------

PROJECT:
Briggsmore Avenue Road Repairs
STATUS:
Work is in progress. Project completion is expected for March 21, 2013
IMPACT:
Work will take place on Briggsmore Avenue between Sisk Road and McHenry Avenue. Traffic controls and lane closures will be in place from 6:30 a.m. to 4:00 p.m. Delays are anticipated. Motorists are requested to travel slowly through the work zone and use alternate routes when possible.

-------------------------------------------------------------------------------------------------------------------

###