Road Repair Report 5/10/13


 
 
Road Repair Update
May 10, 2013
 
-------------------------------------------------------------------------------------------------------------------
PROJECT:
Sylvan Avenue and Litt Road Improvements
STATUS:
Work is in progress. Project completion is expected for August 2013.
IMPACT:
Traffic controls with one narrow lane in each direction are in place along Sylvan Avenue from Millbrook Avenue to Claus Road. Motorists are requested to travel slowly through the work zone and use alternate routes when possible.
Note: Litt Road north of Sylvan Avenue to Plainview Road is closed and will reopen July 2013.
-------------------------------------------------------------------------------------------------------------------
PROJECT:
Carpenter Road Bridge Seismic Retrofit
STATUS:
Work is in progress. Project completion is expected for June 2013.
IMPACT:
Traffic controls are in place with narrow lanes and restricted to alternating, one-way traffic control with flaggers.  Drivers should expect delays. Motorists are requested to travel slowly through the work zone and use alternate routes when possible. Oversized and Wide Load Vehicles should use alternate routes.
-------------------------------------------------------------------------------------------------------------------
PROJECT:
Safety Project by PG&E
STATUS:
Work is on hold. Project completion is expected for June 2013.
IMPACT:
Claratina Avenue from McHenry Avenue to Coffee Road will be restricted to alternating, one-way traffic control with flaggers or intermittently closed. Work will be Monday through Friday, 7:00 a.m. to 5:00 p.m. and Saturday, 9:00 a.m. to 5:00 p.m. Motorists are advised to proceed with caution and pay attention to signage. Drivers should expect to use alternate routes when possible to avoid delays.  Electronic message board signs are in place to alert drivers of the upcoming road work. For further information about this work contact PG&E directly at (559) 317-8857.
-------------------------------------------------------------------------------------------------------------------
PROJECT:
Sanitary Sewer Collection System Replacement
STATUS:
Work is in progress. Project completion is expected for August 2013.
IMPACT:
Work will be ongoing with traffic controls, flaggers and restrictions. Contractor is finishing work on Hackberry Avenue and will be moving to Glenbrook Way and Springcreek Drive early next week to begin work. Motorists are requested to travel slowly through the work zone and use alternate routes when possible.
 
-------------------------------------------------------------------------------------------------------------------
PROJECT:
Gas Main Work by PG&E
STATUS:
Work is on hold. Project completion is expected for June 2013.
IMPACT:
Bangs Avenue from Dale Road to McHenry Avenue will be restricted to alternating, one-way traffic control with flaggers and shoulder work. Work will be Monday through Friday, 7:00 a.m. to 5:00 p.m. Motorists are advised to proceed with caution and pay attention to signage. Drivers should expect to use alternate routes when possible to avoid delays. Electronic message board signs are in place to alert drivers of the upcoming road work. For further information about this work contact PG&E directly at (559) 317-8857.
-------------------------------------------------------------------------------------------------------------------
PROJECT:
Hilltop Area Strengthen and Replace Water System
STATUS:
Work is in progress. Project completion is expected for June 6, 2013.
IMPACT:
Work will be ongoing with traffic controls and restrictions. Work began on Hackberry Avenue between Coldwell Avenue and W. Fairmont Avenue. Other impacted roads include: Dunning Lane, Regal Road, Ridge Road, Hilltop Lane, and Robertson Road. Motorists are requested to travel slowly through the work zone and use alternate routes when possible.
-------------------------------------------------------------------------------------------------------------------
PROJECT:
Bridge Abutment Maintenance Repair on G ,H & I Streets
STATUS:
Work is in progress. Project completion is expected for May 16, 2013.
IMPACT:
G Street & H Street will be reduced to one lane of travel May 8th thru May 16th. Detours will be in place. Motorists are requested to travel slowly through the
work zone and use alternate routes.
-------------------------------------------------------------------------------------------------------------------
PROJECT:
Gas Main Work by PG&E
STATUS:
Work is in progress. Project completion is expected for late-May 2013.
IMPACT:
Dale Road from Bangs Avenue to Standiford Avenue and Sisk Road at Rumble Road will be restricted to alternating, one-way traffic control with flaggers and shoulder work. Work will be Monday through Friday, 7:00 a.m. to 5:00 p.m. Motorists are advised to proceed with caution and pay attention to signage. Drivers should expect to use alternate routes when possible to avoid delays. Electronic message board signs are in place to alert drivers of the upcoming road work. For further information about this work contact PG&E directly at (559) 317-8857.
-----------------------------------------------------------------------------------------------------------------
PROJECT:
CVIN Fiber Optic Underground Placement Project
STATUS:
Work is in progress. Project completion is expected for mid-July 2013.
IMPACT:
Eastbound Orangeburg Avenue from College Avenue to McHenry Avenue and westbound Needham Avenue from McHenry Avenue to College Avenue will be restricted to one lane.  Work will be Monday through Friday, 7:00 a.m. to 5:00 p.m.  Motorists are advised to proceed with caution and pay attention to signage.  Drivers should expect to use alternate routes when possible to avoid delays. 
 

###