Projects Fiscal Year 2018-2019

Project Quarterly Updates

Bike and Pedestrian

Project Status Contact
Dry Creek Trail Maintenance Fact Sheet Preliminary site investigation has begun. Survey has been requested. Engineering design shall begin in a few weeks. Michael Sacuskie

Local Streets and Roads

Projects Status Contact
Claus Road Pavement Rehabilitation Fact Sheet Preliminary site investigation is complete. Project under design. Michael Sacuskie
Downtown Master Plan Fact Sheet No action has occurred. Steve Mitchell
Wylie, Floyd, and Carver Street Improvements Fact Sheet Construction anticipated to begin April 2019. Michael Sacuskie
Village One Slurry Seal 2019 Fact Sheet Preliminary site investigation is complete. Project under design. Michael Sacuskie

Traffic Management

Projects Status Contact
Installation of Rectangular Flashing Beacon Fact Sheet No action has occurred. James Ashby
Fiber Drop into Traffic Signal Cabinet Fact Sheet No action has occurred. Mark Murphy
Replace 35 Obsolete Traffic Controllers Fact Sheet No action has occurred. Scott Collins
Traffic Signal Analysis Study System Wide Fact Sheet Received proposals and hope to have a consultant selected by mid-late October. Scott Collins
Improve Traffic Flow and Safety @ Orville Wright Elementary Fact Sheet Construction anticipated to begin April 2019. Michael Sacuskie