Rancho Encantado Lane and West Hatch Road
Project Status
Expected to be completed and traffic control will be removed by Monday, June 2, 2025.
Traffic Impacts
Road closure to any through traffic with K-rail and detour in place.
- Rancho Encantado Lane and West Hatch Road
Motorists are advised to drive slowly with caution and use alternate routes when possible.
Scenic Drive Pavement Rehabilitation Phase 2
Project Status
Expected to be completed by October 2025.
Traffic Impacts
Lane closure, expect delays between 7:00 a.m. to 5:00 p.m. Monday through Friday
- Scenic Drive from Bodem Street to Oakdale Road reducing traffic to one lane either direction.
- Lane closures on Kansas Avenue from North Carpenter Road to Morse Road.
- Traffic control in place within the Modesto Verde Estates on Hacienda Lane, Celebrity Lane, Festival Lane, and Holiday Lane.
- Bodem Street will be closed to through traffic between Scenic Drive and Downey Avenue
Detour will be in place starting Thursday, May 29, 2025, through Friday, June 6, 2025.
from 8:30 a.m. to 5:00 p.m.
Motorists are advised to drive slowly with caution and use alternate routes when possible.
J.M. Pike Park Storm Water to Sanitary Sewer Cross Connection and Water Main
Project Status
Expected to be completed by the end of June 2025.
Traffic Impacts
Crews will be performing centerline layout and install:
- West of Tully Road between Orangeburg Avenue and Coldwell Avenue
Motorists are advised to drive slowly with caution and use alternate routes when possible.
Well Treatment and Flushline
Project Status
Expected to be completed by the end of June 2025.
Traffic Impacts
Traffic control in place, flaggers, lane, and sidewalk closures as needed.
- South Street in the community of Empire
Motorists are advised to drive slowly with caution and use alternate routes when possible.
Woodland Lift Station
Project Status
Expected to be completed by January 2026.
Traffic Impacts
Periodic traffic control with lane shift and closures.
- on the corner of Woodland Avenue & Poust Road
Motorists are advised to drive slowly with caution and use alternate routes when possible.
Bret Harte Neighborhood Strengthen and Replace
Project Status
Expected to be completed by the end of August 2025.
Traffic Impacts
Partial road closure to through traffic; open to residents.
- Glenn Avenue between Crows Landing Road and Dallas Street
- Seattle Street between Glenn Avenue and Butte Avenue