Scenic Drive
Project Status
Expected to be completed by April 2026.
Traffic Impacts
Lane closure, expect delays between 7:00 a.m. to 5:00 p.m. Monday through Friday
- Scenic Drive from Bodem Street to Oakdale Road reducing traffic to one lane either direction.
- Lane closure at Atwood Drive at intersection of Glenhaven Drive, and Fernview Drive
- Lane closure at Beyer Park Drive at intersection of Hillmont Avenue, Kentwood Avenue and Fernview Drive
Motorists are advised to drive slowly with caution and use alternate routes when possible.
Well Treatment and Flushline
Project Status
Expected to be completed by the end of January 2026.
Traffic Impacts
Traffic control in place, flaggers, lane, and sidewalk closures as needed.
- South Street in the community of Empire
Motorists are advised to drive slowly with caution and use alternate routes when possible.
Woodland Lift Station
Project Status
Expected to be completed by the end of January 2026.
Traffic Impacts
Periodic traffic control with lane shift and closures.
- on the corner of Woodland Avenue & Poust Road
Motorists are advised to drive slowly with caution and use alternate routes when possible.
Tivoli Subdivision
Status
Expected to be open by the end of October 2025.
Traffic Impacts
Traffic control will be in place.
- Westbound lane closure on Sylvan Avenue from Roselle Avenue to Oakdale Road
Motorists are advised to drive slowly with caution and use alternate routes when possible.
Coffee Road Strengthen and Replace
Project Status
Expected to be completed by the end of December 2025.
Traffic Impacts
Expect delays, lane closures, and lane shifts
- on Coffee Road between Orangeburg Avenue and Scenic Drive
- on Coffee Road starting down Multnomah Drive west turning south onto El Vecino Avenue
- Night Work Sunday 10/5/2025 through Thursday 10/9/2025
on Coffee Road between Briggsmore Avenue to Scenic Drive one lane will be closed for northbound and southbound traffic.
Motorists are advised to drive slowly with caution and use alternate routes when possible.
Sewer Trunk Rehabilitation on Grimes, Mercy, and Woodland Avenue
Project Status
Expected to be completed by March 2027.
Traffic Impacts
Traffic control will be in place, expect delays.
- on Grimes Avenue between Paradise Avenue and Maze Boulevard
- on Mercy Avenue between Kansas Avenue and Woodland Avenue
- on Coffee Road between East Fairmont Avenue and Scenic Drive
Motorists are advised to drive slowly with caution and use alternate routes when possible.
North County Corridor Project Status
Expected to be open by October 2026
Traffic Impacts
Detours will be in place beginning Friday, October 3, 2025.
- Roselle Avenue will be closed between Claribel Road and Plainview Road
Motorists are advised to drive slowly with caution and use alternate routes when possible.
Codoni Lift Station
Project Status
Expected to be completed by October 2026.
Traffic Impacts
Periodic traffic control with lane shift and closures.
- on Codoni Avenue between Leckron Road and Finch Road
Motorists are advised to drive slowly with caution and use alternate routes when possible.