PROJECT: STATE ROUTE 99/PELANDALE AVENUE INTERCHANGE RECONSTRUCTION PROJECT
STATUS: Work is in progress. Project completion is expected by 2017.
For the most recent traffic control updates, View This Document
IMPACT:
11/14/16 – 11/18/16 7:00 a.m. – 3:30 p.m.
SB Sisk Road starting 1300ft south of the intersection of Sisk Road/Pelandale Avenue and going approximately 700ft – Closure of the number 1 lane.
11/14/16 – 11/18/16 8:00 a.m. – 3:30 p.m.
NB Sisk Road starting 300ft north of the intersection of Sisk Road/Pelandale Avenue and going approximately 1000ft. – Closure of the number 1 lane.
11/14/16 – 11/18/16 7:00 a.m. – 3:30 p.m.
NB Sisk Road starting 400ft north of the intersection of Sisk Road/Pelandale Avenue and going approximately to the intersection of Sisk Road/Greenleaf Court – Closure of the number 5 lane.
11/14/16 – 11/18/16 7:00 a.m. – 4:00 p.m.
NB/SB Salida Boulevard starting 1200ft south of the intersection of Salida Boulevard/Pelandale Avenue and going approximately 1300ft north from the intersection of Salida Boulevard/Greenleaf Court – Closure of the number 1 lane.
*Note - At least one lane will be open at all times in either direction
11/14/16 to 11/17/16 7:00 a.m. – 3:30 p.m.
SR 99 Southbound On-Ramp & Off-Ramp – Closure of the shoulders only.
11/14/16 to 11/17/16 7:00 a.m. – 3:30 p.m.
SR 99 Northbound On-Ramp & Off-Ramp – Closure of the shoulders only.
11/18/16 7:00 a.m. – 2:00 p.m.
SR 99 Southbound On-Ramp & Off-Ramp – Closure of the shoulders only.
11/18/16 7:00 a.m. – 2:00 p.m.
SR 99 Northbound On-Ramp & Off-Ramp – Closure of the shoulders only.