News Flash Home
The original item was published from 6/15/2023 2:50:58 PM to 6/30/2023 5:05:02 PM.

News Flash

Road Closures & Traffic

Posted on: June 15, 2023

[ARCHIVED] Weekly Traffic Impact Report Week of June 15, 2023

Briggsmore Avenue, Orangeburg Avenue, & Empire Avenue Pavement Rehabilitation Project

Project Status

Work is in progress. Project is expected to be completed by the end of August 2023.

Traffic Impacts

Traffic control will be in place:

  • Lane closures on Briggsmore Avenue from west of McHenry Avenue to east of Oakdale Road.
  • Night work traffic loops Sunday 19th- Thursday 22nd
    (Grinding operation Day work Wednesday 6/14 through Tuesday 6/20) work hours from 0700-2100
    Briggsmore Avenue and Oakdale Road - lane closures 
    Briggsmore Avenue and Sunrise Avenue
    Briggsmore Avenue and Rose Avenue - lane closures 
    Briggsmore Avenue and Coffee Road - lane closures 
  • Orangeburg Avenue (Coffee Road to Oakdale Road)
    Lane closures as needed to maintain chipped surface 
    (Paving on Wednesday 21st & Thursday 22nd) work hours 0700-2100
  • Empire Avenue (Yosemite Boulevard to Tenaya Drive) (Paving on Wednesday Friday 23rd)

Motorists are advised to drive slowly with caution and use alternate routes when possible.

Highway Village Strengthen and Replace Water Mains 

Project Status

Work is in progress. Project is expected to be completed by October 2023.

Traffic Impacts

Traffic control will be in place on the following streets: 

  • Budd Street
  • Crommelin Avenue
  • Whitcomb Avenue
  • Garvey Avenue

Motorists are advised to drive slowly with caution and use alternate routes when possible

New Traffic Signal at Oakdale Road and Claratina Avenue

Project Status

Work is in progress. 

Traffic Impacts

Traffic control will be in place:

  • Oakdale Road & Claratina Avenue

Motorists are advised to drive slowly with caution and use alternate routes when possible.

Sonoma Trunk Extension, Lift Station & Sylvan Water Main Upgrade

Project Status

Work is in progress. Expected to be completed by November 2023.

Traffic Impacts

Traffic control in place shifting traffic to one lane each way, with flaggers, arrow boards and signs as needed:

  • Oakdale Road between Post Office Drive and Mable Avenue
  • Sylvan Avenue between Oakdale Road and Aria Way 
  • Sylvan Avenue is closed to traffic from Oakdale Road to Lydia Lane.  No through traffic permitted. 
  • Detours set from Coffee Road to Roselle Avenue and Claribel Road to Floyd Avenue.

Motorists are advised to drive slowly with caution and use alternate routes when possible.

River Trunk Realignment Gravity System Project

Project Status

Work is in progress.

Traffic Impacts

Construction signs & traffic control is set up and will be adjusted as necessary: 

  • Tuolumne Boulevard – between Colorado Avenue and Neece Drive
  • Lane closures to one lane each way from Colorado Avenue to 99 Freeway
  • Garden Avenue – between Sutter Avenue & Colorado Avenue
  • Closed to through traffic – Local Resident Access Only

Motorists are advised to drive slowly with caution and use alternate routes when possible.

State Route 132 West Freeway Expressway Phase 1 Project

Project Status

Work is in progress. 

Sutter Avenue Strengthen & Replace

Project Status

Work is in progress. Project is expected to be completed by the end of September 2023.

Traffic Impacts

Flaggers and detours will be in place. Impacts will be lane shifts, and partial lane closures

  • on Rouse Avenue between Sutter Avenue and Sunset Avenue 

Motorists are advised to drive slowly with caution and use alternate routes when possible.


Facebook Twitter Email