News Flash Home
The original item was published from 6/22/2023 4:24:24 PM to 7/7/2023 5:05:02 PM.

News Flash

Road Closures & Traffic

Posted on: June 22, 2023

[ARCHIVED] Weekly Traffic Impact Report Week of June 22, 2023

Briggsmore Avenue, Orangeburg Avenue, & Empire Avenue Pavement Rehabilitation Project

Project Status

Work is in progress. Project is expected to be completed by the end of August 2023.

Traffic Impacts

Traffic control will be in place:

  • 6/25 Sunday - Briggsmore Avenue from Mchenry Avenue to Sunrise Avenue Asphalt Rubber Chip: (Night Work)
  • 6/26 Monday - Paving on Briggsmore Avenue from Mchenry Avenue to Sunrise Avenue (Night Work) (8:00 p.m. – 6:00 a.m.) 
  • 6/27 Tuesday, 6/28 Wednesday, and 6/29 Thursday - Briggsmore Avenue from Sunrise Avenue to Oakdale Road Asphalt Rubber Chip: Day Work
  • 6/30 Friday - Paving on Briggsmore Avenue – Sunrise Avenue to Coffee Road– Day Work
  • 7/3 Monday - Paving on Briggsmore Avenue – Coffee Road to Rose Avenue – Day Work
  • 7/5 Wednesday - Paving on Briggsmore Avenue – Rose Avenue to Oakdale Road– Day Work
  • 7/6 Thursday - Paving on Briggsmore Avenue – Rose Avenue to Oakdale Road– Day Work
  • 7/7 Friday - Paving on Briggsmore Avenue between Sunrise Avenue and Oakdale Road – Day Work

Motorists are advised to drive slowly with caution and use alternate routes when possible.

Highway Village Strengthen and Replace Water Mains 

Project Status

Work is in progress. Project is expected to be completed by October 2023.

Traffic Impacts

Traffic control will be in place on the following streets: 

  • Budd Street
  • Crommelin Avenue
  • Whitcomb Avenue
  • Garvey Avenue

Motorists are advised to drive slowly with caution and use alternate routes when possible

New Traffic Signal at Oakdale Road and Claratina Avenue

Project Status

Work is in progress. 

Traffic Impacts

Traffic control will be in place:

  • Oakdale Road & Claratina Avenue

Motorists are advised to drive slowly with caution and use alternate routes when possible.

Sonoma Trunk Extension, Lift Station & Sylvan Water Main Upgrade

Project Status

Work is in progress. Expected to be completed by November 2023.

Traffic Impacts

Traffic control in place shifting traffic to one lane each way, with flaggers, arrow boards and signs as needed:

  • Oakdale Road between Post Office Drive and Mable Avenue
  • Sylvan Avenue between Oakdale Road and Aria Way 
  • Sylvan Avenue is closed to traffic from Oakdale Road to Lydia Lane.  No through traffic permitted. 
  • Detours set from Coffee Road to Roselle Avenue and Claribel Road to Floyd Avenue.

Motorists are advised to drive slowly with caution and use alternate routes when possible.

River Trunk Realignment Gravity System Project

Project Status

Work is in progress.

Traffic Impacts

Construction signs & traffic control is set up and will be adjusted as necessary: 

  • Tuolumne Boulevard – between Colorado Avenue and Neece Drive
  • Lane closures to one lane each way from Colorado Avenue to 99 Freeway
  • Garden Avenue – between Sutter Avenue & Colorado Avenue
  • Closed to through traffic – Local Resident Access Only

Motorists are advised to drive slowly with caution and use alternate routes when possible.

State Route 132 West Freeway Expressway Phase 1 Project

Project Status

Work is in progress. 

Sutter Avenue Strengthen & Replace

Project Status

Work is in progress. Project is expected to be completed by the end of September 2023.

Traffic Impacts

Flaggers and detours will be in place. Impacts will be lane shifts, and partial lane closures

  • on Rouse Avenue between Sutter Avenue and Sunset Avenue 

Motorists are advised to drive slowly with caution and use alternate routes when possible.


Facebook Twitter Email

Other News in Road Closures & Traffic