PROJECT: State Route 99/Pelandale Avenue Interchange Reconstruction Project
STATUS: Work is in progress. Project completion is expected by 2017.
For the most recent traffic control updates, go to: www.SR99Pelandale.org
IMPACT:
12/12/16 – 12/16/16 7:00 a.m. – 3:30 p.m.
SB Sisk Road starting 1300ft south of the intersection of Sisk Road/Pelandale Avenue and going approximately 700ft – closure of the number 1 lane.
12/12/16 – 12/16/16 8:00 a.m. – 3:30 p.m.
NB Sisk Road starting 300ft north of the intersection of Sisk Road/Pelandale Avenue and going approximately 1000ft. – closure of the number 1 lane.
12/12/16 – 12/16/16 7:00 a.m. – 3:30 p.m.
NB Sisk Road starting 400ft north of the intersection of Sisk Road/Pelandale Avenue and going approximately to the intersection of Sisk Road/Greenleaf Court – closure of the number 5 lane.
12/12/16 – 12/16/16 7:00 a.m. – 4:00 p.m.
NB/SB Salida Boulevard starting 1200ft south of the intersection of Salida Boulevard/ Pelandale Avenue and going approximately 1300ft north from the intersection
of Salida Boulevard/Greenleaf Court – closure of the number 1 lane.
*Note - At least one lane will be open at all times in either direction
12/12/16 – 12/15/16 7:00 a.m. – 3:30 p.m.
SR 99 Southbound On-Ramp & Off-Ramp – closure of the shoulders only.
12/12/16 – 12/15/16 7:00 a.m. – 3:30 p.m.
SR 99 Northbound On-Ramp & Off-Ramp – closure of the shoulders only.
12/16/16 7:00 a.m. – 3:00 p.m.
SR 99 Southbound On-Ramp & Off-Ramp – closure of the shoulders only.
12/16/16 7:00 a.m. – 3:00 p.m.
SR 99 Northbound On-Ramp & Off-Ramp – closure of the shoulders only.
12/11/16 to 12/13/16 8:00 p.m. – 5:00 a.m.
SR 99 Southbound & Northbound – closure of lanes 1, 2, & 3.
*Note: At least one lane in each direction will be open
12/11/16 to 12/13/16 10:00 p.m. – 4:00 p.m.
SR 99 Northbound On-Ramp & Off-Ramp – closure of the entire ramp.