PROJECT: STATE ROUTE 99/PELANDALE AVENUE INTERCHANGE RECONSTRUCTION PROJECT
STATUS: Work is in progress. Project completion is expected by the end of February 2017.
For the most recent traffic control updates, go to: www.SR99Pelandale.org
IMPACT:
01/03/17 – 01/06/17 7:00 a.m. – 4:00 p.m.
NB/SB Salida Boulevard starting 1200ft south of the intersection of Salida Boulevard/Pelandale Avenue and going approximately 1300ft north from the intersection of Salida Boulevard/Greenleaf Court – Closure of the number 1 lane.
*Note - At least one lane will be open at all times in either direction
01/03/17 to 01/05/17 7:00 a.m. – 3:30 p.m.
SR 99 Southbound On-Ramp & Off-Ramp – Closure of the shoulders only.
01/03/17 to 01/05/17 7:00 a.m. – 3:30 p.m.
SR 99 Northbound On-Ramp & Off-Ramp – Closure of the shoulders only.
01/06/17 7:00 a.m. – 3:00 p.m.
SR 99 Southbound On-Ramp & Off-Ramp – Closure of the shoulders only.
01/06/17 7:00 a.m. – 3:00 p.m.
SR 99 Northbound On-Ramp & Off-Ramp – Closure of the shoulders only.
01/03/17 to 01/06/17 7:00 a.m. – 3:30 p.m.
NB SR 99 starting 3,000lf south of the new Pelandale Overcross to 2,200lf north of the new Pelandale Overcross – Closure of the shoulders only.
01/03/17 to 01/06/17 7:00 a.m. – 3:30 p.m.
SB SR 99 2,200lf north of the new Pelandale Overcross to 3,000lf south of the new Pelandale Overcross – Closure of the shoulders only.
01/03/17 8:00 p.m. – 5:00 a.m.
NB SR 99 starting 3,000lf south of the new Pelandale Overcross to 2,200lf north of the new Pelandale Overcross – Closure of the shoulders only.
01/03/17 10:00 p.m. – 4:00 a.m.
SR 99 Southbound On-Ramp – Entire ramp closed.
PROJECT: RIVER TRUNK REHABILITATION PROJECT - GALLO SECTION
STATUS: Work is in progress. Project is expected to be completed by the end of March 2017.
IMPACT: Entry way to Gallo at Oregon Drive and South Santa Cruz Avenue is closed to all traffic. Construction signs are set up with minor traffic control. There will be construction equipment moving in this area. Motorists are advised to drive slowly and use alternate routes when possible.
PROJECT: EMERGENCY STORM DRAIN LINE REPAIR ON SCENIC DRIVE BETWEEN ROSE AVENUE AND OAKDALE ROAD
STATUS: Work is in progress. Repair is expected to be completed by January 13th, 2017.
IMPACT: Construction signs are set up with traffic control. Lane closures on eastbound lanes. Heavy equipment moving in and out of the area. Motorists are advised to drive slowly and use alternate routes when possible.