[ARCHIVED] Weekly Traffic Impact Report Week of November 27, 2024

J.M. Pike Park Storm Water to Sanitary Sewer Cross Connection and Water Main

Project Status

Expected to be completed by February 2025.

Traffic Impacts

Minor disruptions, crew will be working:

  • Tully Road between Orangeburg Avenue and Pearl Street 12/2 through 12/6
  • West Roseburg Avenue between Del Vale Avenue and Tully Road 12/2 through 12/6 
  • Princeton Avenue between Kearney Avenue and Carver Road 12/2 through 12/6
  • Del Rey Avenue between Tully Road and Louise Avenue 12/2 through 12/6 
  • Haney Avenue 12/2 through 12/6

Motorists are advised to drive slowly with caution and use alternate routes when possible.

West Trunk Sewer Rehabilitation 

Project Status

Expected to be completed by June 2025.

Traffic Impacts

Detour will be in place at:

  • Dunning Lane between Paradise Road and Regal Road 

Minor disruptions, crews will be working:

  • Dunning Lane between Paradise Road and Robertson Road 
  • Robertson Road between Dunning Lane and South Carpenter Road 
  • South Carpenter Road between Robertson Road and West Hatch Road
  • John Street between Marlow Street and Hays Street 

Motorists are advised to drive slowly with caution and use alternate routes when possible.

La Loma Sewer Phase 1

Project Status

Expected to be completed by June 2025.

Traffic Impacts

Traffic control will consist of lane shifts, flaggers, road closures and detours.

  • Burney Street from Scenic Drive to Jennie Street
  • James Street from Kelley Street to G Street

Including the following residential streets:

  • North Morton Boulevard & Rou De Yoe – Moose Park area
  • Walden Street, Lane Street, Loma Vista Way, Brook Way, & State Street

Motorists are advised to drive slowly with caution and use alternate routes when possible.

Upgrade Traffic Signals  

Project Status

Expected to be completed by June 2025.

Traffic Impacts

Traffic control in place, lane closures, and closing sidewalks as needed.

  • Intersection of 17th Street & I Street 

Motorists are advised to drive slowly with caution and use alternate routes when possible.

Well Treatment and Flushline

Project Status

Expected to be completed by June 2025.

Traffic Impacts

Traffic control in place, flaggers, lane, and sidewalk closures as needed.

  • South Street in the community of Empire

Motorists are advised to drive slowly with caution and use alternate routes when possible.