Road Closures & Traffic

Posted on: August 7, 2025 | Last Modified on: August 7, 2025

[ARCHIVED] Weekly Traffic Impact Report Week of August 7, 2025

Scenic Drive | Neighborhood Improvements | Orangeburg Avenue 

Project Status

Expected to be completed by October 2025.

Traffic Impacts

Lane closure, expect delays between 7:00 a.m. to 5:00 p.m. Monday through Friday

  •  Scenic Drive from Bodem Street to Oakdale Road reducing traffic to one lane either direction.
  • Bodem Street will be closed to through traffic between Scenic Drive and Downey Avenue Detour will be in place from 8:30 a.m. to 5:00 p.m.
  • Lane closure on Robertson Road and Hammond Street
  • Lane closures at Agnes Baptist Elementary: Cheyenne Way (North), Choctaw Way (South), Carver Road (East), and Shawnee Drive (West).
  • Lane closure at Sonoma Elementary School: Orangeburg Avenue, Sonoma Avenue, Zuccaro Way and Meadow Rue Drive.
  • Lane closure at Beyer High School and Stockard Coffee Elementary School: Beyer Park Drive, Kentwood Avenue, Hillmont Avenue, Fernview Drive, 

    Atwood Drive, and Bywood Lane

  • Lane closure at Sarah Avenue and East Orangeburg Avenue

  • Lane closure at Long Court and East Orangeburg Avenue

Motorists are advised to drive slowly with caution and use alternate routes when possible.

Well Treatment and Flushline

Project Status

Expected to be completed by the end of January 2026.

Traffic Impacts

Traffic control in place, flaggers, lane, and sidewalk closures as needed.

  • South Street in the community of Empire

Motorists are advised to drive slowly with caution and use alternate routes when possible.

Woodland Lift Station

Project Status

Expected to be completed by the end of January 2026.

Traffic Impacts

Periodic traffic control with lane shift and closures.

  • on the corner of Woodland Avenue & Poust Road

Motorists are advised to drive slowly with caution and use alternate routes when possible.

Bret Harte Neighborhood Strengthen and Replace 

Project Status

Expected to be completed by the end of August 2025.

Traffic Impacts

Partial road closure to through traffic; open to residents. 

  • Glenn Avenue between Crows Landing Road and Dallas Street 
  • Seattle Street between Glenn Avenue and Butte Avenue 

Motorists are advised to drive slowly with caution and use alternate routes when possible.

Downtown Signal Coordination G Street and H Street  

Project Status

Expected to be completed by November 2025.

Traffic Impacts

Lane closures, lane shifts, detours, and flaggers on site.

  • Scenic Drive from Bodem Street to 18th Street
  • 10th Street through 17th Street in between the G Street and H Street blocks. 

Motorists are advised to drive slowly with caution and use alternate routes when possible.

Tivoli Subdivision

Status

Expected to be completed by August 2025. 

Traffic Impacts

Traffic control will be in place.

  • Westbound lane closure on Sylvan Avenue from Roselle Avenue to Aria Way  

Motorists are advised to drive slowly with caution and use alternate routes when possible.

Coffee Road Strengthen and Replace   

Project Status

Expected to be completed by the end of December 2025.

Traffic Impacts

Expect delays, lane closures, and lane shifts  

  • on Coffee Road between Orangeburg Avenue and Scenic Drive 

Motorists are advised to drive slowly with caution and use alternate routes when possible.

Sewer Trunk Rehabilitation on Grimes, Mercy, and Woodland Avenue 

Project Status

Expected to be completed by March 2027.

Traffic Impacts

Lane closures, expect delays.

  • on Coffee Road between East Morris Avenue to East Fairmont Avenue