PROJECT: STATE ROUTE 99/PELANDALE AVENUE INTERCHANGE RECONSTRUCTION PROJECT
STATUS: Work is in progress. Project completion is expected by 2017.
For the most recent traffic control updates, View This Document
IMPACT:
8/1/16 to 8/5/16 7:00 a.m. – 3:30 p.m.
NB Salida Boulevard starting 400ft south of the intersection of Salida Boulevard/Pelandale Avenue and going approximately 800ft north –
Closure of the single NB lane. Traffic control/flaggers will be in place to allow traffic to pass through using the single SB lane.
*NOTE: Work on Salida Boulevard is anticipated for 1 day only, exact dates of when work will happen depends on crew availability.
8/1/16 to 8/4/16 7:00 a.m. – 3:30 p.m.
SR 99 Southbound On-Ramp & Off-Ramp – Closure of the shoulders only.
8/1/16 to 8/4/16 7:00 a.m. – 3:30 p.m.
SR 99 Nouthbound On-Ramp & Off-Ramp – Closure of the shoulders only.
8/5/16 7:00 a.m. – 2:00 p.m.
SR 99 Southbound On-Ramp & Off-Ramp – Closure of the shoulders only.
8/5/16 7:00 a.m. – 2:00 p.m.
SR 99 Nouthbound On-Ramp & Off-Ramp – Closure of the shoulders only.