The original item was published from 2/8/2019 10:13:53 AM to 2/16/2019 12:00:02 AM.
News Flash
Road Closures & Traffic
Posted on: February 7, 2019[ARCHIVED] Weekly Traffic Impact Report

PROJECT: | BUS TURNOUT IMPROVEMENTS SOUTHBOUND DALE ROAD SOUTH OF VENEMAN AVENUE |
STATUS: | Work is in progress. Project expected to be completed by the end of April 2019. |
IMPACT: | Construction signs will be set up to provide traffic control on:
· DALE ROAD & VENEMAN AVENUE Southbound lane closures are expected, at least one lane of traffic will be open at all times.
Motorists are advised to drive slowly and use alternate routes when possible. |
PROJECT: | ROCK WELL UPGRADE |
STATUS: | Work is in progress. Expected to be completed by the end of February 2019. |
IMPACT: | Construction signs will be placed:
· On PELANDALE AVENUE BETWEEN HONEY CREEK ROAD & DALE ROAD
Lane closures with full traffic control.
Motorists are advised to drive slowly and use alternate routes when possible. |
PROJECT: | LA LOMA NEIGHBORHOOD PHASE 2B FIRE HYDRANT ADDITIONS |
STATUS: | Project is expected to start 2/19/19 and completed by April 2019. |
IMPACT: | Construction signs & street closed signs will be in place.
· ENCINA AVENUE to YOSEMITE BOULEVARD · SAN JUAN DRIVE to EL VISTA AVENUE
Neighborhood streets will be closed to through traffic during construction and opened at the end of each day. Main streets will have lane closures during time of construction and open to traffic at the end of each day. Motorists are advised to drive slowly and use alternate routes when possible.
|
Additional Info...