Posted on: September 8, 2016

[ARCHIVED] Traffic Impact Report

PROJECT: STATE ROUTE 99/PELANDALE AVENUE INTERCHANGE RECONSTRUCTION PROJECT

STATUS: Work is in progress. Project completion is expected by 2017.
For the most recent traffic control updates, View This Document

IMPACT:

9/12/16 to 9/16/16 7:00 a.m. – 3:30 p.m.
NB/SB Salida Boulevard starting 1200ft south of the intersection of Salida Boulevard/Pelandale Avenue and going approximately 1500ft north – Closure of the shoulders only.

9/12/16 to 9/16/16 7:00 a.m. – 3:30 p.m.
EB Pelandale Avenue starting 300ft west of the intersection of Sisk Road/Pelandale Avenue and going approximately to the intersection of Sisk Road/Pelandale Avenue – Closure of the number 3 lane.

9/12/16 to 9/16/16 7:00 a.m. – 3:30 p.m.
NB Sisk Road starting at the intersection of Sisk Road/Pelandale Avenue and going approximately 200ft. north – Closure of the number 2 lane.

9/12/16 – 9/16/16 7:00 a.m. – 3:30 p.m.
SB Sisk Road starting 1300ft south of the intersection of Sisk Road/Pelandale Avenue and going approximately 700ft – Closure of the number 1 lane.

9/12/16 – 9/16/16 8:00 a.m. – 3:30 p.m.
NB Sisk Road starting 300ft north of the intersection of Sisk Road/Pelandale Avenue
and going approximately 1000ft. – Closure of the number 1 lane.

9/12/16 – 9/16/16 7:00 a.m. – 3:30 p.m.
NB Sisk Road starting 400ft north of the intersection of Sisk Road/Pelandale Avenue
and going approximately to the intersection of Sisk Road/Greenleaf Court – Closure of the number 5 lane.

9/12/16 to 9/15/16 7:00 a.m. – 3:30 p.m.
SR 99 Southbound On-Ramp & Off-Ramp – Closure of the shoulders only.

9/12/16 to 9/15/16 7:00 a.m. – 3:30 p.m.
SR 99 Northbound On-Ramp & Off-Ramp – Closure of the shoulders only.

9/16/16 7:00 a.m. – 2:00 p.m.
SR 99 Southbound On-Ramp & Off-Ramp – Closure of the shoulders only.

9/16/16 7:00 a.m. – 2:00 p.m.
SR 99 Northbound On-Ramp & Off-Ramp – Closure of the shoulders only.

9/12/16 to 9/15/16 7:00 a.m. – 3:30 p.m.
SB/NB SR 99 starting 2,200lf north of the new Pelandale Overcross to 3,000lf south of the new Pelandale Overcross – Closure of the shoulder only.

9/16/16 7:00 a.m. – 2:00 p.m.
SB/NB SR 99 Southbound starting 2,200lf north of the new Pelandale Overcross to 3,000lf south of the new Pelandale Overcross – Closure of the shoulder only.