[ARCHIVED] Weekly Traffic Impact Report

Traffic Control Measures in relatively close proximity to a construction site.

Project:

Area 2 Storm Water to Sanitary Sewer Cross Connection

Status:

Work is in progress. Project is expected to be completed by the end of December 2019.

Impact:

Construction signs will be in place for street closures during working hours on:

  • Pearl Street & Bronson Avenue
  • Carlton Avenue to West Granger Avenue
  • College Avenue to Albany Avenue
  • Orangeburg Avenue & College Avenue

Motorists are advised to drive slowly with caution and use alternate routes when possible.

-----------------------------------------------------------------------------------------------------------------------------

Project:

Bermuda Way Strengthen & Replace Water Mains

Status:

Work is in progress. Project is expected to be completed by March 2020.

Impact:

Traffic will be impacted.

  • Sherwood Avenue just north of Orangeburg Avenue
  • Bermuda Way
  • Balboa Way
  • Coronado Way
  • Catalina Way

Motorists are advised to drive slowly with caution and use alternate routes when possible.

-----------------------------------------------------------------------------------------------------------------------------

Project:

Crows Landing Sewer Trunk

Status:

Work is in progress. Project is expected to be completed by April 2020.

Impact:

Traffic will be impacted. Construction signs will be set up to provide traffic control:

  • Crows Landing Road from Zeff Road to Crater Avenue
  • Crater Avenue from Crows Landing Road to Cascade Avenue

Motorists are advised to drive slowly with caution and use alternate routes when possible.

-----------------------------------------------------------------------------------------------------------------------------

Project:

Empire Sanitary Sewer Trunk

Status:

Work is in progress. Project is expected to be completed by January 2020.


Impact:

Construction signs will be set up to provide traffic control on:

  • Garner Road at Yosemite Boulevard
  • Yosemite Boulevard from Garner Road to A Street in Empire
  • A Street from Yosemite Boulevard to 1st Street
  • 1st Street from A Street to Church Street
  • C Street from Yosemite Boulevard to the first alley

Motorists are advised to drive slowly with caution and use alternate routes when possible.

-----------------------------------------------------------------------------------------------------------------------------

Project:

Wylie Floyd Carver Street Improvements

Status:

Work is in progress.

Impact:

Floating lane closure on:

  • Floyd Avenue between Coffee Road and Oakdale Road
  • Carver Avenue between Pelandale Avenue and 9th Street

Motorists are advised to drive slowly with caution and use alternate routes when possible.

-----------------------------------------------------------------------------------------------------------------------------

Project 

Right Turn Lane Improvements West Bound D Street North Bound 9th Street

Status:

Work is in progress. Project is expected to be completed by February 2020.

Impact:

Construction area signs and detour routes will be set up with minor traffic control at:

  • D Street and 9th Street No right turns will be permitted from east bound D Street onto 9th Street

Motorists are advised to drive slowly with caution and use alternate routes when possible.

-----------------------------------------------------------------------------------------------------------------------------

Project:

McHenry Avenue & Stewart Road

Status:

Work is in progress. Project is expected to be completed by August 2020.

Impact:

There will be construction signs and minor traffic control, with possible lane closures where traffic will shift to maintain two traffic lanes.

  • McHenry Avenue and Stewart Road
  • Motorists are advised to drive slowly with caution and use alternate routes when possible.

-----------------------------------------------------------------------------------------------------------------------------

Project:

Village One Slurry Seal

Status:

Work is in progress.

Impact:

Traffic will be impacted for striping layout.

Floating lane closures on:

  • Floyd Avenue from Oakdale Road to Claus Road
  • Roselle Avenue from Kodiak Drive to Belharbour Drive
  • Motorists are advised to drive slowly and use alternate routes when possible.

-----------------------------------------------------------------------------------------------------------------------------

Additional Info...